Dependencies and lag
FS, SS, FF, SF dependency types and lag.
Project ManagersProject Manager Last updated 13 Aug 2026
Dependencies
A dependency links two tasks so that scheduling one affects the other.
Dependency types
- FS (Finish-to-Start) — the successor starts when the predecessor finishes. The most common type.
- SS (Start-to-Start) — the successor starts when the predecessor starts.
- FF (Finish-to-Finish) — the successor finishes when the predecessor finishes.
- SF (Start-to-Finish) — the successor finishes when the predecessor starts.
Lag
Lag is a delay (in days) added after the predecessor before the successor can start. A lag of 2 means "wait 2 working days after the predecessor finishes."
Creating a dependency
- Open a task → Details tab → linked tasks section, or
- On the Timeline, drag from the right edge of one bar to another.
The critical path is calculated from your dependencies — it's the longest chain that determines the project finish date.